Civic Centre Resource Library – April 10
As of this week, the primary structural steel appears to be complete. Installation of the secondary steel such as trim edges is ongoing. Metal decking installation is complete on the first level, and is approximately 60% complete on the second … Continue reading Civic Centre Resource Library – April 10